Keeping a hospital alive while you rebuild its veins
There is no 'off switch' on a live hospital. Tying new theatres into old risers means choreographed shutdowns measured in minutes, with clinical staff in the room when the valve turns.
Marwa El-Sayed
Commissioning Manager, Green Square
Refurbishing an occupied hospital is the most honest test of a contractor's planning culture. Every tie-in to a live system (medical gas, chilled water, critical power) is a negotiated event with clinical leadership, not a line on a programme.
The anatomy of a 40-minute shutdown
A single riser tie-in can carry a week of preparation: isolation surveys signed by three parties, temporary supplies proven under load beforehand, a written abort path at every step, and a rehearsal, a real one, with the team walking the route and speaking the calls. On the night, the clinical liaison stands next to our supervisor, and either of them can stop the job with one word.
- Permit-to-work with clinical counter-signature, always
- Temporary plant proven at load before the isolation, not after
- Wards briefed in person; alarms expected, never explained away
- Recovery verified on trend data before the team stands down
“In a hospital, the most important tool on a shutdown is the word 'stop', and everyone holds one.”
We carried this culture through our Riyadh medical city delivery, where commissioning meant deliberately failing systems a hospital depends on, before the hospital depended on them. The playbooks from those nights now travel with our healthcare teams to every clinical site we touch.